The Sindh Govt has taken a major decision regarding the Karachi Bus Rapid Transit project. It has terminated the construction contract for a key section of the BRT Red Line. The move comes after repeated delays in project delivery.
Senior Minister Sharjeel Inam Memon confirmed the decision on Wednesday. He said the contract for the Mosamiyat to Numaish section has been cancelled. The contractor failed to meet deadlines despite several warnings.
The Sindh Govt said it had tried to resolve issues with the contractor. These included concerns related to cost adjustments and rate escalation. However, the progress remained slow and unsatisfactory over time.
Officials explained that the project is important for Karachi’s transport system. The BRT Red Line is expected to reduce traffic pressure on University Road. It is also designed to improve public transport facilities in the city.
Construction work on the project had restarted in November. This happened after several bottlenecks were removed. The intervention of the Chief Minister helped restart the work. Still, the project continues to face delays.
Commuters in Karachi are still facing difficulties due to ongoing construction. Travel on major routes remains slow and disrupted. The Sindh Govt acknowledged these challenges and said urgent action was needed.
The Asian Development Bank, which is financing the project, has also expressed concern. It raised issues about the slow pace of work. Environmental stakeholders have also highlighted concerns about the project’s impact.
To address delays, the Sindh Govt has announced a new strategy. The remaining construction work will be divided into smaller packages. These will be awarded to multiple contractors.
Officials believe this approach will speed up progress. It is expected to improve efficiency and reduce further delays. The aim is to complete the BRT Red Line in a shorter timeframe.
In other related news also read preparation for KP CM’s Sindh visit
The Sindh Govt said it remains committed to improving Karachi’s transport infrastructure. Authorities hope the revised plan will ensure better coordination and faster completion of the project for public benefit.