The contract termination for Lot 2 of the Karachi BRT Red Line project has been declared unlawful.

The Dispute Resolution Board described the Sindh government’s decision as unlawful, invalid, null and void.

The board issued its decision after the Sindh High Court referred the dispute for resolution. The case involves the Sindh government and contractor AM Associate.

The court directed both parties to use the dispute resolution process required under their contract. The board then conducted hearings for more than two months.

Lot 2 covers the section of the Karachi BRT Red Line between Mosamiyat and Numaish. The Sindh government had terminated the construction contract over concerns about slow progress.

AM Associate challenged the termination before the Sindh High Court. The contractor also accused the provincial government of delaying the project.

After reviewing the dispute, the board found that the contract had been terminated prematurely. It said authorities failed to properly consider other options before ending the agreement.

The board also raised concerns about TransKarachi’s ability to manage the project. TransKarachi is the government-owned agency responsible for implementing the project.

According to the board, TransKarachi lacked the institutional capacity required for such a large project. It also lacked sufficient experienced project management for the project’s complexity.

The board identified several contractual obligations that TransKarachi had not fulfilled. These issues were present when construction work started.

One major issue involved the project design. The board found that the design had not been finalized.

The government also failed to provide the contractor with the full project site. The site was required to be free from obstacles for construction work.

Another issue involved substantial outstanding payments. The board said these unpaid amounts affected the contractor’s ability to perform the work.

The board concluded that these problems contributed to delays in project implementation. It said the contractor faced difficulties because of these unresolved issues.

The board also criticized repeated changes to the project design. Weak coordination between relevant parties was another concern.

Delayed decisions and ineffective contract administration were also mentioned in the ruling. These issues further affected progress on the project.

The board said there was insufficient evidence that authorities had seriously considered alternative solutions.

It found that contract termination was not the only available option. The decision should have followed a more measured approach, according to the board.

The board ultimately ruled that the termination was premature. It also stated that termination was not used as a last resort.

The decision marks an important development in the ongoing dispute surrounding the Karachi BRT Red Line project.

The ruling also highlights broader concerns about project management and contractual responsibilities.

The project is intended to improve public transportation and connectivity across Karachi. However, construction has faced several challenges during its implementation.

The dispute over Lot 2 has added another issue to the project’s development process. The latest ruling could influence the next steps involving the construction contract.

The Sindh government and AM Associate will now have to consider the board’s decision under their contractual framework.

The case also highlights the importance of timely payments, finalized designs and effective coordination. These factors are important for completing major infrastructure projects on schedule.